A) 48
B) 32
C) 64
D) 43.5
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) 12 days
B) 6 days
C) 18 days
D) 9 days
Correct Answer
verified
Multiple Choice
A) The project manager cannot force subcontractors to use this project management approach.
B) The feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team.
C) Subcontractors routinely operate according to calendar delivery dates.
D) The corporate culture of "no blame" does not naturally extend to subcontractors.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Slack buffers.
B) Drum buffers.
C) Rope buffers.
D) Feeder buffers.
Correct Answer
verified
Multiple Choice
A) 13
B) 17
C) 26
D) 35
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) CCPM is a complete solution to current project management scheduling needs.
B) In a multi-project environment where resources are shared, it is impossible to avoid multitasking.
C) There is substantial large-scale empirical research that confirms the efficacy of CCPM.
D) Lack of milestones within CCPM make coordination with external suppliers and subcontractors much easier.
Correct Answer
verified
Multiple Choice
A) Requirements are allowed to float throughout the duration of the project.
B) Customer needs change quickly.
C) Time constraints exist.
D) Budget constraints exist.
Correct Answer
verified
Multiple Choice
A) Project workers are more likely to meet a deadline for their activity than miss it.
B) There are no milestones in the CCPM activity network.
C) Project workers are more likely to miss a deadline for their activity than meet it.
D) There is no project delivery deadline in the CCPM activity network.
Correct Answer
verified
Multiple Choice
A) Frequent communication among programmers, but infrequent communication with the customer.
B) Understanding the problem completely before coding begins.
C) A hierarchical management structure.
D) Avoidance of programming features until they are actually needed.
Correct Answer
verified
Multiple Choice
A) 0
B) 1
C) 2
D) 3
Correct Answer
verified
Multiple Choice
A) As late as possible.
B) As early as possible.
C) Before starting the critical path.
D) After completing the critical path.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) 24
B) 18
C) 8.41
D) 4.24
Correct Answer
verified
Multiple Choice
A) 8.5 days
B) 17 days
C) 24.5 days
D) 34 days
Correct Answer
verified
Multiple Choice
A) Scrum meeting > Sprint
B) Scrum master > Development team
C) Sprint time box > Project duration
D) Daily scrum duration < Development work duration
Correct Answer
verified
Showing 81 - 100 of 101